In this video, Attorney Philip Hundl provides a timely update on the Kinder Morgan Trident Pipeline. If you’re impacted by this or any other pipeline project, you should get the help of a knowledgeable lawyer to guide you through the condemnation process. Call Philip at 800-266-4870 or text the office at 979-320-9320. Our offices are in Wharton County, and we help landowners all over Texas.
Summary of Kinder Morgan Trident Pipeline: Final Offers Sent, Condemnation Filings Coming Next
Attorney Phil Hundl provides a timely update on the Kinder Morgan Trident Pipeline—a 216-mile, up to 48-inch diameter, high-pressure natural gas project impacting several Texas counties. With final offers now delivered, landowners should prepare for the next step: condemnation filings.
Key Takeaways for Landowners:
- Most affected landowners have now received final offer letters with appraisals
- Condemnation petitions are expected soon—don’t be surprised if you’re served
- It’s critical to speak with an attorney experienced in eminent domain to protect your rights and understand the process
Project Overview: Route and Counties Impacted
The route begins in Katy, loops around the north side of Houston, and continues southeast into Jefferson County.
Counties impacted include:
- Waller
- Grimes
- Harris (portions)
- Walker
- San Jacinto
- Liberty
- Jefferson
Current Stage: Final Offers and Appraisals Delivered
Many landowners along the proposed route have now received:
- Initial offer letters
- Final offer packets, which include formal appraisals
Next Step: Condemnation Filings Expected
Philip warns landowners to expect condemnation petitions to be filed soon by Kinder Morgan’s legal team, which includes three different law firms. This is a common part of the eminent domain process when a pipeline company cannot secure easement agreements through negotiation.
Legal Guidance Strongly Recommended
If you are a landowner who has received either an initial or final offer and haven’t yet spoken with an attorney, now is the time to act. An attorney experienced in eminent domain can help you:
- Understand your rights
- Navigate the condemnation process
- Ensure that Kinder Morgan follows the legal procedures required by Texas law
Related Links
- Trident Pipeline Update – Understanding the Initial Offer Letter
- Trident Pipeline Alert for Landowners – TROs and Temporary Injunctions
- Trident Pipeline Alert for Landowners: TROs and Permanent Easement Concerns
- Trident Pipeline Update: Temporary Access and Landowner Rights
- Texas Landowners: Are You Impacted by the Trident Pipeline?
Call 800-266-4870 or text 979-320-9320 for an appointment. We can also arrange for online and telephone appointments all over Texas.